This project aims to enhance wastewater conveyance efficiency in the area by the installation of approximately 5,620 linear feet of 12-inch and 18-inch gravity main along Porter Creek, extending from the Lift Station to Dairy Road and Cotton Gin Road. The project is undertaken by contractor EVT Construction, LLC. The total estimated construction cost of $879,586.79. The completion date is April 17, 2025.