This project includes the installation of approximately 14,860 linear feet of 8-inch, 12-inch, 18-inch, and 21-inch gravity wastewater main along FM 2720, extending westward to PCU 3 on Misty Lane. The project, undertaken by contractor Dale Lowden Excavating, LLC. The estimated construction cost is included with construction cost of FM 2720 Water Main. The project is estimated to be completed by August 5, 2025.